A DeBordieu Dock Permit Has Three Owners. Here Is Who Signs, Who Dredges and Who Pays.

November 19, 2026

A private dock on a DeBordieu canal or creek lot needs three sign offs: a state critical area permit from SC DES under regulation R.30-12, written approval from the DeBordieu Colony Community Association's Architectural Review Board, and a Georgetown County building permit. The owner maintains the dock. Canal dredging has been paid two ways: from the association's reserve fund and by a neighborhood assessment on the lots that benefit.

Key Takeaways

  • R.30-12 sets the hard limits: no private dock on a creek under 10 feet wide, size caps by creek width, and 75 feet of marsh frontage for lots subdivided after May 23, 1993.
  • DeBordieu's ARB guidelines (revised January 17, 2026) require the SC DES permit and a county building permit with the dock application, and prohibit covered docks.
  • The 2018 canal dredging was funded partly by a neighborhood assessment of $13,853 per canal front property, approved by the 75 percent owner vote the 1986 covenants require.

Walk a DeBordieu canal lot with a buyer and the dock is usually the first thing they point at. Sometimes there's one already. Sometimes there's a stretch of marsh and a picture of what could go there. Either way, the listing tends to treat the dock as a feature of the lot.

It isn't, exactly. A dock in DeBordieu belongs to three different rulebooks, each with its own signature, and the water under it belongs to a fourth conversation about who pays to keep it deep enough to use. You're paying a premium for a canal lot. The question is how much of that premium you can actually use, and what it costs to keep using it.

That's the part that almost never makes it onto the listing sheet.

The state decides whether a dock can exist at all

The first owner of your dock is the State of South Carolina. Private docks over the critical area are permitted by SC DES under regulation R.30-12, and the numbers in it are specific. A lot subdivided after May 23, 1993 needs 75 feet of frontage at the marsh edge, and 75 feet between extended property lines where the dock would go. No dock is permitted on a creek under 10 feet wide, measured marsh to marsh. Under 20 feet, the answer is generally no, with a narrow exception capped at 50 square feet and no boat lift.

Above that, size scales with the creek: 120 square feet of total dock for creeks 20 to 50 feet wide, 160 for 51 to 150 feet, and up to 600 for creeks wider than 150 feet. Docks stay 20 feet off extended property lines, walkways max out at four feet wide, and lifts must be open sided.

Context matters here too. DeBordieu drains into North Inlet, part of the North Inlet Winyah Bay National Estuarine Research Reserve, and the state classifies North Inlet and lower Debidue Creek as Outstanding Resource Waters under R.61-69. Those are some of the most protected waters on the coast, which is part of why they look the way they do.

One more thing worth knowing in 2026: a SC DES stakeholder workgroup report from February 2026 recommended raising the minimum creek width for docks. Those are recommendations, not amended rules. Read the regulation in force on the day you apply.

The association decides what the dock can look like

The second owner is the DeBordieu Colony Community Association. The community's Declaration of Covenants, recorded May 9, 1986 in Georgetown County at Book 235, Page 805, allows docks only under the declarant's regulations and government approval, and puts maintenance on the owner, with 30 days to fix a defect once the association gives notice.

The ARB's guidelines, revised January 17, 2026, spell out the rest. No dock goes up without ARB approval and current, dated written approval from the state. The dock application has to include the state permit and the Georgetown County building permit. Covered docks are prohibited. Boat lifts need their own ARB approval. Docks aren't allowed on the golf course or inland ponds. The ARB review fee for a dock on salt water, tidal or finger canals is $250.

The association's Boat Decal Policy, revised March 15, 2025, covers the community ramp and boat dock, not your private one: boats are trailered and removed, with no overnight storage, and decals run $15 per boat.

The neighbors decide who pays to keep the water there

The third owner is everyone else on the canal. A dock is only as useful as the water at low tide, and canal water gets shallower over time.

The association's own 2018 dredging materials lay out how that was paid. The section from the Boat Basin to Debidue Creek came out of the reserve fund. The incremental canal work was paid by a Neighborhood Assessment: $13,853 per canal front property across 62 properties, $4,618 for Marsh Creek properties and $2,309 for Royal Tern, paid in two installments in September and December 2018, to a target depth of 3.5 feet below mean low water. The covenants allow a neighborhood area assessment when 75 percent of the owners in that area petition for it. The FAQ noted earlier dredging in 2001 and 2011 to 2012 and said the work was expected to last eight to ten years, or longer.

Eight to ten years from 2018 is now. Whether the next round is on the agenda, and how it would be funded, is a question for the association, and the public site doesn't post current dredging reserves. That's an honest gap, and it's the right question to ask before you write the offer, not after.

Across the county line, the dock in the photo is a different question

On the Horry side of Murrells Inlet, the conversation about creek docks is less about an association's rulebook and more about whether the permit on file matches the structure you see. I wrote about that in In Murrells Inlet, the Dock in the Photo Isn't Always Part of the Deal. The state rules are the same. What changes in DeBordieu is the second and third layer: an ARB with its own standards and a canal whose depth is a shared, assessed cost.

Layer

Who signs

What it controls

Record to request

State

SC DES, Bureau of Coastal Management

Whether a dock is allowed, size, length, setbacks

Critical area permit and any assignment or transfer

Association

DeBordieu ARB

Design, lifts, covers, location

ARB approval letter and as built plans

County

Georgetown County building department

Construction permit

Building permit and final inspection

Canal

Owners in the neighborhood area (75 percent vote)

Dredging and depth

Most recent dredging assessment and reserve information

What this means if you're deciding

If there's an existing dock, ask for the state permit before you write the offer. According to the legacy SC DHEC critical area FAQ, an active permit can be assigned to a new owner through an assignment and transfer form, work must be completed within five years of issuance, and expired permits can't be extended. A dock without a matching permit is a different conversation than a dock with one.

If there's no dock, measure two things before you price the premium: the marsh frontage and the creek width. Those two numbers decide whether R.30-12 allows a dock and how big it can be. A surveyor and SC DES make that call, not a listing description.

Then ask the association, through the resale certificate and the HOA addendum to the disclosure form, about special assessments levied (Q3) and whether the property is subject to the Coastal Zone Management Act (Q10). Ask directly about the next dredging cycle.

For the ownership costs that sit on top of a DeBordieu purchase, read The DeBordieu List Price Is Only Half the Story. The DeBordieu community page and the home search show current canal and creek listings.

A Few Common Questions

Who issues a dock permit in DeBordieu?
SC DES issues the state critical area permit under R.30-12. The DeBordieu ARB must also approve the dock, and its guidelines require a Georgetown County building permit with the application.

Can a dock be built on any DeBordieu creek lot?
No. R.30-12 bars private docks on creeks under 10 feet wide, and lots subdivided after May 23, 1993 need 75 feet of marsh frontage. Covered docks are prohibited by the ARB.

Does a dock permit transfer to the buyer?
An active permit can be assigned through an assignment and transfer form, according to the state's critical area FAQ. Expired permits can't be extended.

Is canal dredging in DeBordieu paid from dues or a special assessment?
Both have been used. In 2018 the Boat Basin section came from the reserve fund and the incremental canal work was paid by a neighborhood assessment of $13,853 per canal front property.

Can I see the dock permit before I make an offer?
Yes, ask the listing side for it. The state's FAQ directs permit questions to the regional SC DES office in Myrtle Beach.

Megan Parker has spent her life around these creeks and knows the difference between a dock in a photo and a dock in a permit file. She'll pull both before you pay for either. Let's Connect.

About the author: Megan Parker is a second generation Realtor with Berkshire Hathaway HomeServices Coastal Real Estate, licensed in South Carolina (Lic. #119738), serving DeBordieu, Pawleys Island, Litchfield, Prince George, Georgetown, Murrells Inlet and the Grand Strand. Sources: SC DES Regulation R.30-12 (history through May 23, 2025); SC DES Regulation R.30-2; SC DHEC critical area permitting FAQ (legacy page); SC DES Dock Stakeholder Workgroup Final Report (Feb. 2026); R.61-69 Classified Waters (amended May 26, 2023); Declaration of Covenants and Restrictions for DeBordieu Colony (recorded May 9, 1986, Bk. 235 Pg. 805); DCCA ARB Architectural Guidelines (rev. Jan. 17, 2026); DCCA dredging FAQ and July 27, 2018 voter information package; DCCA Boat Decal Policy (rev. Mar. 15, 2025); NOAA NERRS North Inlet Winyah Bay; SC LLR disclosure statement and HOA addendum (updated 6/2025). This article is general information, not a permitting, legal or survey determination; confirm any property specific question with SC DES, a surveyor or an attorney. Information deemed reliable but not guaranteed. Berkshire Hathaway HomeServices Coastal Real Estate. Equal Housing Opportunity.

More Market Insights

From Megan's Desk

Choosing an Agent to Sell a Pawleys Island or Litchfield Home Starts With Five Documents, Not a Price

Compare the brokerage relationship, the license record, the coastal disclosure plan, dated market data and the listing agreement.

From Megan's Desk

A DeBordieu Dock Permit Has Three Owners. Here Is Who Signs, Who Dredges and Who Pays.

SC DES permits the dock, the DeBordieu ARB approves its design, and canal owners have paid for dredging by neighborhood assessment.

From Megan's Desk

The Grand Strand's Christmas Parades All Happen in Nine Days. Here Is the Whole 2026 Calendar.

Seven parades run Dec. 4 to Dec. 12. Every 2026 holiday date from Loris to Georgetown.

Quiet Cherry Grove residential canal with a small timber dock and pale elevated beach houses in soft autumn morning light.
Cherry Grove's Canal Homes Come With a Dredge Schedule

From Megan's Desk

Who Pays If Pawleys Inlet Moves Again? The Cost Line Inside the 2025 Settlement

The settlement assigns inlet relocation to the Town and Prince George; a south end owner's cost runs through flood and setback rules.

Aerial view of a waterfront town with a boardwalk, green parkland, and low-rise buildings.

Neighborhood Guides

The Market Common Was Paid For Before It Was Built. The Bonds Run Through 2036.

Before the shops and the lake, the city built a financing plan on an empty air base. That plan still decides what a Market Common address really means.

Residential homes in a Myrtle Beach South Carolina neighborhood
Myrtle Beach Housing Inventory: What Sellers Need to Know

More listings don't always mean falling prices. What's happening in your neighborhood and price range tells a much more useful story.

Raised blue beach house with a front porch on the dunes, Myrtle Beach, SC
Myrtle Beach Homeowners Insurance: What Buyers Should Know

Two coastal homes can have the same price tag and very different insurance costs. Here's what buyers should know before making an offer.

Couple riding a blue golf cart down a wooded neighborhood path in coastal South Carolina

Taxes, Fees and Rules

How to Own a Golf Cart in South Carolina in 2026: The $5 Permit Is the Easy Part

Registration, insurance, and the local rules that change from one Grand Strand town to the next, checked against the statute as amended in May 2026.

Work With Megan

From buying and selling to real estate investing, Megan Parker delivers trusted guidance, local market expertise, and personalized solutions tailored to your goals. Her client-focused approach ensures a smooth, successful experience at every stage of your real estate journey.