November 19, 2026
Before the City of North Myrtle Beach began dredging Cherry Grove's canals, some canal-front lots sat on dry land at low tide. That was how MyHorryNews described conditions in the finger canals off House Creek. When the City drew up its plan for the Cherry Grove Improvement District in 2015, dredging was the only improvement on it. The stated goal was to bring back navigation at low and high tide, which had worn away over the decades since the canals were dug.
On a Cherry Grove canal, the water at the end of the dock has a price and a schedule. Canal-front owners have paid for two dredges since 2016, through a line item City Council sets each year. That line item ends in 2028, and a third, deeper dredge of the main channel is already in the permitting and budgeting records. Before you compare two canal homes on list price, find out where that schedule stands.
The 2015 plan expected a cycle from the start. It scheduled an initial dredge for autumn 2015 into winter 2016 and a maintenance dredge for autumn 2020 into winter 2021, depending on canal conditions. Its design target was 3 feet of water at low tide in the finger canals and 3.5 feet in the main canal.
The actual dates ran later than planned, but the pattern held:
| First dredge | Second dredge | |
|---|---|---|
| When | November 2016 to April 2017 | 2022 to 2023, listed complete in September 2023 |
| Area | Canals from 42nd to 62nd Avenue North | Access canals and much of the Minor Channel |
| Money | $7.84 million total, with $6.7 million from residents and $1.15 million from the City | $3,242,000 Series 2022 bond; construction estimated at about $2.7 million |
| Paid off | 2016 bond repaid in full | Bond scheduled through April 1, 2028 |
The first dredge was costly for each lot. MyHorryNews reported that owners paid $2,400 a year for five years. The City's 2015 plan proposed total assessments of $24,000 for a standard single-family parcel, $48,000 for a double lot and $16,560 for a multifamily parcel. In the same reporting, City spokesperson Pat Dowling said some owners had to dredge around their own docks to reach the center cut, because their property lines extended into the canals.
The second dredge was a bigger job. The City's April 2022 project scope called for hydraulic dredging of about 140,000 cubic yards across roughly 26,000 linear feet. The spoil was pumped about 20,000 feet to Horry County's Tidewater Disposal Basin, also known as Disposal Area 320, near Tidewater Plantation on the Intracoastal. The pipeline ran under Little River Neck Road through an existing conduit. Beam & Associates was the engineer and Michels Construction was the contractor. City Public Works reports showed the job 60% complete in May 2023 and complete by September 2023.
On June 15, 2026, City Council adopted Resolution RES 26-16, which sets the Cherry Grove assessments for the 2026–2027 year. According to the City's staff memo, the autumn 2026 billing is $1,720.67 for each single-family parcel in the district and $1,187.26 for each condominium. The total revenue needed for 2026–2027 debt service and administrative costs is $714,730.87. The district administrator's report dated June 3, 2026 counts 414 single-family parcels and two condominium parcels that haven't prepaid and so receive that annual bill.
The bill has barely changed in three years. Council set it at $1,725.20 per home and $1,190 per condo at its July 15, 2024 meeting. For 2025–2026 it was $1,718.75 and $1,185.94.
The end date matters most to a buyer this winter. The City's memo says the annual updates will continue until the second assessment bond, issued in November 2022, is paid in full in April 2028. As of the June 3, 2026 report, the total special assessment still outstanding across the district was $2,566,723.47. If you close on a canal home now, the current cycle's bill is near its end. You are also buying into a neighborhood where a dredge is a recurring cost, and the next one is already taking shape.
These figures are general information drawn from public City records, not legal, tax or financial advice. Confirm how they apply to a specific property with the right professional before you rely on them.
The design depths are the most practical part of the record for anyone picturing a boat behind the house. The 2022–2023 dredge cut the Minor Channel 34 feet wide to 3 feet below mean low water. Access canals were cut 24 feet wide, to 3 feet for about two-thirds of their length and 2.5 feet for the rest, with one foot of allowable overdredge.
Two homes on the same canal can therefore sit on different design depths, and half a foot of water counts when you are choosing a boat's draft or planning a run out toward Hog Inlet at low tide.
Council members have tied the dredging directly to how the water gets used. In the July 15, 2024 Council minutes, Councilman Bubba Collins said fishing had been good that summer because of the dredging. Then–Mayor Pro Tem Jo Baldwin said the channels would have dried up without it and hoped the main channel could be included in future dredges.
Baldwin's hope about the main channel already appears in federal and City records. A U.S. Army Corps of Engineers public notice published January 5, 2024, SAC-2023-01503, describes a proposed dredge of Cherry Grove's Major Canal. It would remove about 25,000 cubic yards per event, in three events totaling 75,000 cubic yards, on a five-to-seven-year maintenance cycle. The proposed depths are 5 to 6 feet below mean low water, deeper than the 2.5 to 3 feet cut in the access canals. The spoil would also go to the Tidewater site, by a pipeline route through House Creek.
The City's FY2026 budget retreat document lists a "CG Main Channel Dredge" at $1,000,000 for FY2026 among its proposed capital projects, alongside items such as fire trucks and Fire Station #7. At the June 15, 2026 Council meeting, Councilman Thomas asked whether the dredging permit had been used up and where the City stood on the maintenance dredge. Mayor Baldwin answered that a permit extension had been requested.
Cherry Grove's canals have been maintained in planned rounds since 2015, with a first dredge, a second about six years later, and a deeper main-channel project proposed on its own five-to-seven-year cycle. When you value a Cherry Grove canal home, include the cost of keeping that channel open alongside the dock, the bulkhead and the view.
If you're comparing Cherry Grove with canal and marsh property elsewhere on the Grand Strand, our post on how docks work as permits in Murrells Inlet covers a related question from a different angle. Our waterfront market trends post and the North Myrtle Beach neighborhood guide round out the picture.
Has the bill gone up as the bond is paid down? Not meaningfully. The single-family amount was $1,725.20 in 2024, $1,718.75 for 2025–2026 and $1,720.67 for the autumn 2026 billing.
Where does the dredged material go? For the 2022–2023 dredge, it went by pipeline to Horry County's Tidewater Disposal Basin near Tidewater Plantation. The proposed main-channel project names the same site.
If a Cherry Grove canal home is on your list, let's talk through the dredge record and what you want from the water before you write an offer. Reach out to Megan Parker and let's connect.
From Megan's Desk
Compare the brokerage relationship, the license record, the coastal disclosure plan, dated market data and the listing agreement.
From Megan's Desk
SC DES permits the dock, the DeBordieu ARB approves its design, and canal owners have paid for dredging by neighborhood assessment.
From Megan's Desk
Seven parades run Dec. 4 to Dec. 12. Every 2026 holiday date from Loris to Georgetown.
From Megan's Desk
The settlement assigns inlet relocation to the Town and Prince George; a south end owner's cost runs through flood and setback rules.
Neighborhood Guides
Before the shops and the lake, the city built a financing plan on an empty air base. That plan still decides what a Market Common address really means.
More listings don't always mean falling prices. What's happening in your neighborhood and price range tells a much more useful story.
Two coastal homes can have the same price tag and very different insurance costs. Here's what buyers should know before making an offer.
Taxes, Fees and Rules
Registration, insurance, and the local rules that change from one Grand Strand town to the next, checked against the statute as amended in May 2026.
From buying and selling to real estate investing, Megan Parker delivers trusted guidance, local market expertise, and personalized solutions tailored to your goals. Her client-focused approach ensures a smooth, successful experience at every stage of your real estate journey.